The master bedroom / bathroom, and now our fireplace framing is complete!
The garage and bonus room:
Master bath, bedroom 4, family room and morning room patio door:
The rear of the house all wrapped and ready with windows and a decent amount of shingles done:
Bedroom 2, the dining room, and the board covering the egress window:
The patio door frame:
The entry door and the garage fire door are the last two left:
The stairs to the basement. Anyone else's stairs have the particle board risers on it like here? I would think that on an exposed stairs (our basement is unfinished for now) that it would have been solid boards for both.
The morning room with patio door:
The garage windows:
The loft / entry windows:
A closer look at the patio door:
All in all one busy busy week! Week 5 should be the finishing of the roof, as well as all of the trades get in there and get the rough wiring, low voltage wiring, and hvac in place for Week 6 and the all important pre-drywall inspection!